Thursday 9th July 2020
Exciting progress at Middlefields House
THURSDAY 9 JULY 2020
We are pleased to report that progress has continued to be good at the Middlefields House site, and that the project is running to schedule.
On site works continue to progress well despite the disruption caused by the COVID-19 pandemic. Procurement of materials that had previously been slipping as a result of the virus has now stabilised.
Looking ahead over the next month, it is intended to finish the masonry works, the concrete plank floors and staircases, and to start the roof trusses at the beginning of August.